I have a question regarding EA2.3 As I understand it, it appears that the ongoing Cx process effectively begins with EAc2.1 and EAc2.2. The ongoing Cx plan must also include budgets and schedules for repeating this work at a given frequency, etc. My question is: Do we need to confirm and document that the implemented changes in EAc2.2 were implemented correctly in EAc2.2, EAc2.3, or neither? Can we simply state what changes were made as part of the deficiency resolution or do we need to submit proof that it was resolved? Thanks