If our project has a water reduction of 30% but is not installing any urinals or kitchen taps, what clauses should be included for the tenant? Should the tenant be obliged to install fixtures and fittings that, whenever calculated together with the fixtures we have installed, retain that 30% reduction?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Mike D
56 thumbs up
May 10, 2013 - 6:45 am
Hello all,
Can anyone help out with this? We are very confused as to what condition should be set for the tenants.
Many thanks for your help!
Jim Park
Project ManagerEAN Technology
21 thumbs up
May 22, 2013 - 9:44 pm
When fixtures are not selected before DP submission, I usually ask mechanical engineers to require specs to achieve with 30% reduction. I am not sure completely, but I believe that you need to specify GPM/GPF of urinals and kitchen taps. If urinals or kitchen taps are not included in WEp1 calculation, reviewers will certainly will ask you to clarify it.