When a project would be classified under Major Renovation (our project is around 80% renovated) for the energy model, does the baseline have to be the same as Ashrae 90.1 envelope requirements or can it be the based on the current conditions to be demolished?
Thanks.
Anthony Hardman
Building Performance AnalystThe Green Engineer
16 thumbs up
April 24, 2013 - 5:10 pm
All existing buildings can be modeled with pre-retrofit conditions in the baseline case according to Table G3.1(5)(f)(baseline).