I'm working on an option D M&V plan according to LEED. The building is heated and cooled with gas heat pump, therefore the electricity consumption just includes fan/pump power, process load and lighting. If I have just whole building electric meter, can I use the following declaration to divide the electricity consumption in three parts? 1. pumps and fans (constant volume fan) electricity consumption: calculated with energy demand and run time 2. process load electricity consumption: calculated with occupancy time and energy demand. 3. lighting electricity consumption: subtract from the whole building electricity consumption. Is it necessary to divde the electricity consumption separately? Thanks!