FAQs about EAp2 :

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

Can I claim exterior lighting savings for canopy lighting even though a baseline model cannot include shading elements?

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

For a project outside the U.S., how do I determine the climate zone?

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

The Section 9 space-by-space method does not include residential space types. What should I use?

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

Part of Factory is designed but won't be installed now

Dear community, I am wondering how I should read the language of the 90.1 in the following case: - My project includes lots of process and related HVAC, which have been designed to 90% completion stage according to the turn-key terminology - But an important part of the process will not be installed at this stage and therefore the construction drawings won't show this part, neither in terms of machine process nor in terms of related HVAC. Only provisions are there. If I read the 90.1 2007 I can find only the following, which is related to the topic: "When the performance rating method is applied to buildings in which energy related features have not yet been designed (e.g., a lighting system), those yet-to be-designed features shall be described in the proposed design exactly as they are defined in the baseline building design. Where the space classification for a space is not known, the space shall be categorized as an office space." Clearly, according to this statement, I should model the project as it is event thought it won't be installed now and that we don't have the construction drawings wich will correspond to the very future installation. "Where the HVAC zones and systems have not yet been designed, thermal blocks shall be defined based on similar internal load densities, occupancy, lighting, thermal and space temperature schedules, and in combination with the following guidelines" In this case again, it is pretty clear that what defines the condition to simulate a generic space is the condition of whether or not it has been defined. Now, in both these statement, I see one point which is not clear: "not yet designed" for LEED means "not emitted the construction drawings" or "not designed at all"? You see my worry is that I do not define the baseline properly if this very point is not clear. Thank you for your clarifications,

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 01/30/2013 - 15:18

This is a bit of grey area. You may be able to ignore it or you could include it. How far off in the future is the design and installation? If it is several years a way I might be tempted to ignore it. If imminent after construction I would try to include it. The standard would probably fall on the not designed at all side of your question. If you include it and it has not been designed then those sections of the standard you mention basically say it must be modeled identically if it has not been designed.

Thu, 01/31/2013 - 06:28

Well in this case I think I really have to include it. The missing part on the construction drawings has been designed and allowed for in the provisioned capacities of chillers and boilers. Only there won't be construction drawings for now. But there are non-final detailed drawings already detailing the systems. In addition, it would be weird to have this part of the factory turned into offices (and thus we would have to give it more office type thermal approach more dealing with envelope which would be inconsistent with the rest of the factory's design). It seems to me that the language tends to have us include it. right?

Thu, 01/31/2013 - 13:56

That sounds right to me based on what you have shared.

Add new comment