FAQs about EAp2 :

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

Can I claim exterior lighting savings for canopy lighting even though a baseline model cannot include shading elements?

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

For a project outside the U.S., how do I determine the climate zone?

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

Table G3.1.1 exceptions b and c interaction

Dear all, We have a facility with lots of process areas having pressurization and code-related minimum circulation rates. As a result, we say that all the process areas HVAC system baseline switch from system 7 to system 3. But also, the administrative part of this project has thermal loads that differ significantly from the rest of the project, therefore, they should also switch from system 7 to system 3. At the end of listing the applicable exceptions, I happen to have a baseline project, which is originally system 7, entirely switched in system 3. Although this is quite positive from the point of view of my project's scoring, I wonder if this is right reading of the Appendix G. It is the combination of the two exceptions that makes it so. But if my process areas are swithced to system 3 due to exception c, should I still consider exception b? Is there a "linear" way of reading these exceptions or should I say "because most of the project is in system 3, the exception b does not apply and my administration building stays in system 7"? Thank you for the help, With Best Regards,

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 12/26/2012 - 16:31

Take the square footage of the predominant condition (likely the process areas) and enter table G3.1.1A. Select the system. If heated only you can use system 9 or 10 from 90.1-2010. You can then apply exception b to the administrative areas and likely model system 3. You can not take an exception for both areas.

Mon, 12/31/2012 - 10:06

Hi, The thing is that my project falls under the 90.1-2007 according to the project's registration date and corresponding rating system. I thought so that I could not apply exceptions to both areas (but where is it written?). Moreover, process areas are heavily cooled. Therefore, I take the predominant condition, indeed the process area, and I go to table G3.1.1A. System 7 corresponds to my case. Then I apply the exception G3.1.1c which makes the system 7 becomes system 3. Then, the predominant condition for my project becomes system 3. Therefore is the remaining administration area just system 7 as a consequence of the initial category of the project or does it become also system 3, not because of the exception, but because according to table G3.1.1.A? The process area is quite an exception because of the process requirements in regards to overpressurization. I am not sure how to not end up with system 3 only baseline model...

Mon, 12/31/2012 - 17:03

You can apply addenda to 90.1-2007 and this would allow the use of system 9 or 10 but it sounds like it does not help you anyway. The note under Table G3.1.1A indicates you must apply the predominant condition. You then apply exceptions. It is just implied logic that you cannot have a project made up of exceptions - exceptions to what? You cannot take an exception to your predominant condition. Since the System 7 was selected based on the predominant condition you then apply exceptions to areas outside the predominant area. Given the widespread applicability of exceptions in your case perhaps you could break your project down into more distinct areas so that the exceptions might apply to a larger area. But you cannot have the entire baseline system comprised of exceptions. A significant percentage of the project must me modeled using one of the systems from Table G3.1.1A.

Add new comment

To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.