The first sentence in the reference guide describing Stage 2 certification notes that the Building square footage must be "fully entitled." The architect on the job has asked what that term means. Any help here?
Hi Chris,
By "entitlement" we're referring to land use entitlements, not building permits. From the LEED-ND FAQ:
"LEED-ND defines entitlements as 'the existing or granted right to use a property for the specific types and quantities of residential and nonresidential land uses proposed, either by right or through a local government regulatory change process.' A good rule of thumb to determine stage eligibility is to consider whether a project team needs to take their proposed plan or a portion of their proposed plan through the various rounds of land use approvals or whether a project team can build their proposed mix of uses based on their site’s existing zoning and regulatory environment. If yes to the former, a project team’s site is likely most eligible for Stage 1. If yes to the latter, a project team’s site is likely most eligible for Stage 2."
Meghan