We are reviewing a project for LEED certification (v 2.2) that was designed and constructed by another firm. There are documentation and template form issues with the Recycled content/Regional credits-we are trying to figure out the best way to correct the errors since the contractor is no longer in the picture and we probably can't get them to revise their information.
Is possible for us to 'redo' the contractor forms ourselves? We have access to the submittal and cost information and can get additional documentation info from the manufacturer. The contractor''s LEED consultant signed all their forms so we are hoping it wont an issue if our names are on the form instead. If anyone has had any experience with this your thoughts on the issue would be appreciated.
Thanks!