Hi all, I am currently working on a large project including an aquatic center. We plan to use geothermal energy to cover around 90% of the heat required for pool heating. We are considering pursuing a LEED NC certification for this aquatic center but need some clarification on how to address EAp2 and EAc1. It seems to me that pool-related energy is considered as process energy in ASHRAE 90-1, and must therefore be identical for both Baseline and Proposed buildings. Since it accounts for a large part of the energy consumption, I’m wondering how we can achieve those credits (and prerequisite!!) ? I’m also struggling to model such a building accurately following ASHRAE 90-1 requirements. Thanks in advance for your advices! Regards