The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

For a project outside the U.S., how do I determine the climate zone?

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

The Section 9 space-by-space method does not include residential space types. What should I use?

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

Building Envelop Requirement on Manufacturing facility

I am working on a winery facility which includes office spaces and manufacturing spaces. Does LEED NC require the building envelop parameters (e.g. U-values, SC) of manufacturing parts of the facility space meet ASHRAE 90.1 Building Envelop Requirements as well?

1

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Thu, 05/10/2012 - 19:15

The envelope requirements are not mandatory provisions so no specific level of window or envelope performance is required anywhere. The manufacturing part of the facility will have to include the minimum envelope values in the Baseline model just like the office.

Tue, 05/15/2012 - 21:26

Do I understand correctly that compliance with the mandatory provisions (sections 5.4 - 10.4) are required to achieve ANY points for EAc1? For example if the building has a motor that does not comply with section 10.4 but the energy simulation shows an overall improvement of 14% over baseline, can the building still achieve the extra points?

Tue, 05/15/2012 - 22:34

The mandatory provisions are required for this prerequisite which must be earned before any EAc1 points can be awarded. If you don't meet the prerequisite you cannot earn LEED certification at all. So the answer to your first question is yes and the second question is no.

Wed, 05/16/2012 - 16:40

Thank you Marcus, your reply answers my questions related to equipment efficiency but I still have a doubt related to section 5.4 and your answer to Xun Jia above. After reading section 5.4 carefully I cannot see where the envelope and glass requirements are not mandatory for the appropriate Climate Zone. I know I must be missing something but really cannot find where. Thanks again.

Wed, 05/16/2012 - 17:19

Section 5.4 can be confusing. I am guessing you are looking at some of the mandatory provisions like 5.4.1 and are confused. This section only applies to the insulation material characterisitics, not the level of insulation. Sometimes in 90.1 you need to connect the dots to make sense of it, so make sure you read the definitions and each of the referenced sections before coming to a conclusion. The insulation levels in Tables 5.5-1 to 5.5-8 are part of the prescriptive section 5.5 and are not included in the mandatory provision section 5.4.

Add new comment