We have a project over 50,000 sf in DD phase and are in early talks with a potential Facility Manager. Can a FM or a disinterested party from that FM firm serve as a CxA for EAc3?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Chris Ladner
PartnerViridian
261 thumbs up
March 9, 2012 - 11:24 am
The short answer is "Yes" as long as the FM is not part of the design team. Just make sure the provider complies with the experience requirements shown in the reference guide.