We have a master plan campus project for which we are trying to acheive several credits which, once achieved, can then be easily shared and applied for in the 3 individual projects which will eventually be on the site.

So far only 1 of the 3 buildings is ready for LEED documentaiton and it has 260 FTE. However we have estimated that the total project wil have 960 FTE when completed.

What is the best way to comply with the 5% or more of all building users rule with regards to bicycle storage for Pilot Credit 13?

I presume that we should comply with the estimated 960 FTE figure, but if there are no confirmed building plans yet for the the other 2 future buildings it's quite difficult to show the storage location on a plan, presuming we can't fit it all on the site for the first building.

Any suggestions welcome! Thanks