FAQs about EAp2 :

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

The Section 9 space-by-space method does not include residential space types. What should I use?

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

Can I claim exterior lighting savings for canopy lighting even though a baseline model cannot include shading elements?

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

Existing Building undergoing major renovation

ASHRAE 90.1 states that existing buildings shall be modeled as is before renovations. Currently the building has all of the window openings boarded up. I'm thinking that the best scenario would be to model the area of the window openings to be consistent and assign a u-value associated with plywood to the "window" and a SHGC of 0. Has anyone encountered this situation before, if so is this logic correct? Thanks.

4

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 11/30/2011 - 21:54

I think you need to apply some sense of logic to these situations. As an example, would it be appropriate to model an existing condition as an open hole in the wall even if that was the case? Assuming that the current opening will be filled with windows I would model windows in the baseline. If this is an old building that had windows, I would likely model single pane windows in the baseline, not plywood. If this was a newer building, say built since the common use of double pane glass, I would use a double pane window. If the building had metal frames, I would use that in the baseline. If wood frames, I would use that. There are values in Table A8.2 for unlabeled vertical fenestration you could use as a default.

Wed, 11/30/2011 - 22:02

Based on ASHRAE fundamentals, the u-values are almost identical for 5/8 inch plwood and single pane windows from Table A8.2.

Wed, 11/30/2011 - 22:32

Sounds right and with a SHGC entered for the windows your baseline will be a more thermodynamically comparable model to the Proposed.