I am working on a project that is definitely going to pursue LEED certification (required) but would like to delay the registration process. The project is being built in phases which might be part of their hesitancy. If we waited till the end of construction documents for the last portion to register the project would that be a problem? would we still be eligible to have both a design and construction submittal?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Emily Catacchio
Sustainability SpecialistWight and Company
610 thumbs up
October 27, 2011 - 9:50 am
I think Tristan's comment below addresses this very well. I would add that LEED is meant to influence the design, so waiting for construction to finish would make it difficult to get certified. I don't see the benefit in waiting.