I'm having trouble finding a dfinition for "Occupancy" We want to pursue IEQc3.2 using Option 1,Path 2 for a movie theater. Can we bring in staff for training during the initial delivery of 3,500 cf of outdoor air / sf? After this phase is complete, we will open the building to patrons and operate normally while the balance of the flush out is completed.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
David Hubka
Director of OperationsTranswestern Sustainability Services
527 thumbs up
June 3, 2011 - 10:41 am
Commissioning can occur during the flush-out if it does not introduce any additional contaminants into the building. Enhanced Commissioning requires owner training. . . so yes, training can occur during the flush-out; provided the training does not introduce any additonal contaminants.
To be proactive, you may want to include a narrative outlining how additional contaminants were not introduced during the flush-out due to the trainings. The LEED review team may require this narrative.
Hope this helps!