I have been asked to bid a LEED CI project where there will only be flooring, wall relocation, and added ceiling tiles to 7,000 feet of a 50,000 foot office space. There will be no plumbing relocation or additions. There will be no HVAC, however, some of the ductwork may be relocated. How do I meet the minimun requirements or prerequisites? Can the project be exempt from these requirments if they are not part of the project scope? How do I do this? Would Commissioning be exempt?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
I would expect the LEED project reviewer would still require you to meet the six items of the Owner's Project Requirements. (see page #124 of the LEED CI reference guide)
The LEED online template allows you to check "Included" "Partial" or "N/A" for each of the MEP systems that require commissioning. If every item is checked as "N/A" you would most likely check the special circumstances box and include a narrative describing your project scope.
Hope this helps.
You can however claim exemption from the Water prerequisite if plumbing isn't in the scope