We have already got review comments for our project.However,we now realized that in the simple payback calculations we have by mistake given a totally wrong value for the 'lighting retro fitting'.Is it acceptable by USGBC that we change the value and amend the payback period??My worry is that it will be totally different from what we submitted previously.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Pierce Holstrom
Director of EngineeringEnvironmental Building Strategies
69 thumbs up
August 11, 2010 - 3:02 pm
It's never too late to change your calculations to better reflect your project. LEED works best when dealing with the most accurate information and it sounds like your lighting retrofit calculation is better now than when you submitted it. Is your team pursuing EAc2.2?