I am filling the LEED online template for EA p2, and I face a problem. Now I can get the building unmet load hours from eQUEST BEPS report, but I don't know how to split the heating unmet load hours and cooling unmet hours. Pls help, thanks.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Christopher Schaffner
CEO & FounderThe Green Engineer
LEEDuser Expert
963 thumbs up
August 9, 2010 - 8:28 pm
I believe the SS-R report in the DOE2 output will break each zone down by heating and cooling unmet hours.