Kevin, this is one of those situations where the submittal requirement doesn't have a whole lot of bearing on the actual level of operational performance at the project building. This requirement to upload a site plan was added in v2009 to create continuity between the SS credits, but isn't really relevant to the key criteria for SSc2. If you are using a site plan to highlight features for other SS credits (SSc5, SSc6, SSc7, or SSc8), feel free to use the same file here. However, you may also provide separate versions of the site plan for those individual credits in order to clearly show the information that is appropriate for the corresponding credit. For example, landscaping strategies may be clearly highlighted for SSc5, but a different version of the file might be used to clearly illustrate location of parking structures for SSc7.1.