EAp2 LEED Online form

1

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Mon, 05/17/2010 - 00:03

The target finder numbers should be based on the energy model, which would reflect the entire building, including tenant spaces.

Wed, 06/30/2010 - 16:38

If following the prescriptive option allowed under EAp2, an energy model will not (most likely) be put together. And how would an energy model deal with vacant, unleased tenant spaces, where interior design and loads are not known??

Wed, 06/30/2010 - 23:01

Future tenant spaces get modeled as occupied spaces. You need to assume a likely use, pretty easy if it is an office building. Any systems that are not yet installed (lighting, for example) get modeled as minimally code compliant.