Yes. Even if a tenant controls the refrigerant containing equipment, you’ll have to include it in the building inventory. The only exception is that project teams may exclude up to 10% of the building floor area for separately managed spaces. See the LEED Reference Guide on more details for this type of exclusion.

Question
<p>We don’t control tenant supplied supplemental cooling equipment for uses like server closets, data centers, etc. Are we required to address the tenant equipment for the prerequisite?</p>