Yes, USGBC's "Water User Reduction Additional Guidance" (10/17/2016 v9), projects may count future infrastructure such as reclaimed water systems as longas they are "functional within 2 years of project occupancy." Anything further out than two years may not be counted, however.

Question
Can project teams include reclaimed water systems that are planned and funded, but not completed?