According to GBCI, any significant issues uncovered during the commissioning process should be noted in the required commissioning report. A narrative and/or supporting documentation must be provided to summarize the corrected issues and outline any outstanding issues, as well as include detailed information on the plan for correcting any outstanding issues. However, evidence that the follow-up was completed and systems corrected is not be required.
Question
The comissioning process turned up a few issues with the commissioned systems that should be corrected. Do we have to correct these issues and include documentation of that as part of our LEED documentation?