The CxA cannot directly authorize construction change orders or changes to the design documents. The commissioning authority’s responsibility is to inform the project owner of findings and their effect on building performance. It is the owner’s responsibility to choose a proper course of action. The CxA will document all issues and resolutions over the course of the project.

Question
What level of authority does the CxA have towards correcting inaccurate or erroneous construction?