The short answer is no, but it’s still good to do it. If the project team decides to pursue MRc7, MRc8 and/or MRc9, they will have to provide documentation and/or calculations demonstrating compliance for those credits. However, for this prerequisite (MRp2), demonstrating performance during the performance period is not required.

Question
To comply with MRp2, the Solid Waste Management Policy must state goals associated with the requirements of MRc7, MRc8, and MRc9. Does the project team need to track the performance of these related credits’ goals during the performance period?