Bldg Footprint_Cooling Tower & Generator

CS-2009 SSc5.1:Site Development—Protect or Restore Habitat
posted by  Nancy Goshow  on 

We have a cooling tower and emergency generator adjacent to our building that is on a concrete pad and surrounded by a screen enclosure. Should this area count as part of the building footprint?

1
Wed Jul 27, 2011, 11:00 pm

Instantaneous and/or totalized

EBOM-2009 EAc3.2:Performance Measurement—System-Level Metering
posted by  James Gray  on 

For natural gas metering applications, is continuous logging of instantaneous flows a requirement? Most meters just put out totalized pulses, so I'm assuming that's fine... Any thoughts?

0

Designated smoking area in a loading dock

EBOM-2009 IEQp2:Environmental Tobacco Smoke (ETS) Control
posted by  Jessica Jones  on 

Can you please comment on whether the following approach would be acceptable to achieve this prerequisite: A project building is attached to a loading dock on the property, and the designated smok

1
Tue Nov 1, 2011, 2:32 pm

Floated tile paving and Heat Island Effect

EBOM-2009 SSc7.2:Heat Island Reduction—Roof
posted by  Mauricio Ramirez  on 

I have a building that has in the most part of their roof, a floating tile paving, that creates an air-chamber between the slab of the roof and the tilies of the paving.

1
Fri Sep 2, 2011, 2:15 pm

MPR supplement re parking garage no longer cerifiable

General forums
posted by  joseph porrovecchio  on 

The change applied to parking garage certification is unfortunate and short sighted.

1
Sun Jul 10, 2011, 10:05 am

Percentage of finished floor complying for the credit

Schools-2009 IEQc4.3:Low-Emitting Materials—Flooring Systems
posted by  Dario Ibarguengoitia  on 

MY QUESTION IS.. WHAT IF I JUST HAVE 25 % OF THE FINISHED FLOOR AREA USING LOW EMITTING OR CERTIFIED PRODUCTS, AM I STILL EARNING THE CREDIT?

1
Sun Jul 24, 2011, 4:40 am

Re: Addition to LEED Certified Building

General forums
posted by  David Posada  on 

I've not heard of re-submitting an already certified building other than pursuing EBOM.

0

Calculator

EBOM-2009 EAc1:Optimize Energy Performance
posted by  Austin Evans  on 

In the Case 2 Option 2 tab for the offline calculator the cells are locked up on the option III enter current year EUI score as far as I can tell.

1
Wed Oct 5, 2011, 3:41 pm

Gross Lighted Area - ASHRAE 90.1-2007

CI-2009 EAc1.1:Optimize Energy Performance—Lighting Power
posted by  Trevor Karstens  on 

This topic was previously posted under EAp2, but was not getting any responses; this seems like the more relevant location anyways: I'm encountering difficulty in documenting the minimum 10% light

1
Wed Aug 17, 2011, 2:57 pm

Does Automation promote integrated design?

General forums
posted by  Nadav Malin  on 

On the page about Pilot Credit 5 John Albrecht proposed that Automation enabled project management tools can help make the design process more integrated.