Forum quick links
Enclosure Cx Provider
NC-v4 EAc1:Enhanced commissioningposted by Brett Farbstein on
The project is pursuing v4. A 3rd party Cx provider has been engaged for MEPs.
Using VAV box CFMs as measurement of outside airfow
EBOM-2009 IEQc1.2:IAQ Best Management Practices—Outdoor Air Delivery Monitoringposted by Sean Blaevoet on
Will GBCI accept monitoring of VAV box CFMs as measurement of outside airflow during "economizer" mode?
Commercial Kitchen
CS-2009 IEQc8.2:Daylight and Views—Viewsposted by José Solis on
I have a mixed use office building with the potential for restaurant tenants on the ground floor.
Flush-Out Requirement for a Naturally Ventilated Building
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Eric Carbonnier on
The project is an 8 story residence hall on a university campus. The building is not equipped with a central ventilation system and dorm rooms rely on natural ventilation.
Regional Priority points not being awarded?
CS-2009 RPc1:Regional Priorityposted by Ashley Love on
I just received our Design Final Review back and we have three credits (WEc3, EAc1, and IEQc7.1) that we have been awarded that are also regional priority credits.
MBCx scope for LEED-CI
CI-v4 EAc1:Enhanced commissioningposted by Mark Benson on
The project scope includes new HVAC equipment & controls as well as occupancy sensors for lighting control.
Green Cleaning in a Fab
NC-2009 IDc1:Innovation in Designposted by David Gibney on
I'm working on a semiconductor fab that is part of a LEED campus project. The campus has a well-established, campus-wide green cleaning program in place.
CO Sensors in Multi-Family Highrise
NC-v4 EQp1:Minimum indoor air quality performanceposted by Jennifer Rennick on
For a Multi-Fam Highrise, the corridors will be heated with a ducted roof-top gas furnace split dx system will be installed.
Functional entryway of project
CS-v4 LTc5:Access to quality transitposted by Martin Stowell on
For this credit, 'functional entry of the project' means from the project boundary or the actual building?
How to specify for v4 LEED compliance
Data-Centers-NC-v4 MRc2:Building product disclosure and optimization - environmental product declarationsposted by Lissa Spitz on
Any recommendations on specs for the v4 MR credits? For example, we used to say 10% recycled materials required.