Alternative Compliance Path Case 1: Lease Document
CI-2009 EAc3:Measurement and verificationposted by Carolina Acevedo on
Is there an alternative compliance approach to this credit? My project falls under Case 1 (less than 75% of the project space), but my client owns the floors hence the lack of a lease agreement.
Undefined Outdoor Spaces
CS-2009 SSc6.1:Stormwater design - quantity controlposted by Luis Miguel Diazgranados on
Greetings Everyone I'm working on a office project with outdoor spaces within the LEED Boundary. The project's construction phase is almost finished.
Material-Efficient Framing based on LEED-Homes?
NC-2009 IDc1:Innovation in designposted by Heather DeGrella on
Has anyone tried an ID point for NC, based on the Material-Efficient Framing credit in LEED for Homes?
Determining Baseline for Mixed Use
NC-2009 EAp2:Minimum energy performanceposted by Jason Biondi on
Hi all, thanks for the forum. The building is 8 stories, 3 flrs office, 3 floors parking, 1 retail, 1 resturaunt. Is it accepabable to use the 5 story building baseline schedule if the parking gara
Water deduct meters acceptable as submeter?
EBOM-2009 WEc1:Water performance measurementposted by Ryan Nelson on
Could a water deduct meter be used as a working submeter assuming it properly segregates systems such as the cooling tower or irrigation?
LEED Boundary/Gross Floor Area for LEED-CI project
NC-2009 PIf2:Project Summary Detailsposted by Silvia Ruiz on
1. In calculating the gross floor area of an office located in a building with curtain walls, would the measurement be taken from the exterior face of the curtain wall?
Completing PIF1 when you have an exception to providing meters
NC-2009 MPR6:Must commit to sharing whole-building energy and water usage dataposted by Susan Di Giulio on
We are working on a municipal water processing plant.
option 3 requirements
CI-2009 IEQc8.1:Daylight and views - daylightposted by Adam Targowski on
Are there any requirements regarding the time of the day when the daylight measurements have to be taken?
Owner's Policy, or Cleaning Contractor's Policy?
EBOM-2009 IEQp3:Green cleaning policyposted by Margaret McColl on
Hello, I am working on a project that is owned an occupied by a single company that uses a cleaning contractor. Does the Green Cleaning Policy have to be developed and implemented by the Owner?
Landscape factors
CS-2009 WEc1:Water efficient landscapingposted by CRolim Engenharia on
Hi! In my project, certain areas just has trees and ground cover. For these areas , i will use the landscape factors for mixed trees, shrubs and groundcovers? Thank you!