question
posted by Tarek Dalati on
my project is composed of a 52 residential building and 2 retails (g+1 and G+2) they are in the same project boundary and fed from the same HVAC systems ( chillers and boilers) the retails are bas
Treatment of District or Campus Thermal Energy in LEED 2009
posted by Henry Mak on
hi, we are working on a project which consists of 5 buildings and only 2 of them will go for LEED certification. AGMBC approach has been applied.
GSF for Master Site?
posted by Erin Holdenried on
I have a new campus project where two of the seven buildings are getting certified. So, we have a Master Site registered and two individual building registrations.
New to AGMBC
posted by Anthea Ng on
Hi everyone, here is a new comer of LEEDuser. Umm... after reading the LEED online block set up instruction, grateful if I could have more rigid advices.
EBOM and multiple buildings
posted by Kathleen Burke on
It should not be this complicated-i hae 2 office buildings with parking below. One building is 3 stories and the other is 8-do i have to register each of these separately or?
Part II Multiple Buildings funcitonality
posted by Karen Joslin on
This is Q3 2012 and we still don't see the option for Part II projects at LEED Online?
Multiple Buildings and Registration
posted by Kathleen Burke on
I have 2 office buildings for EBOM-I talked to someone about the registration and Part 2 of that document is not ready to use and this person said there was no known date that it would be release
LEED gym on campus
posted by maartje van roosmalen on
Hi, I'm new here so apologies if this question has been raised elsewhere already.
Any rules for certifying attached buildings as one building?
posted by Aaron Yorke on
Hello All, We have two buildings which are attached on the first level (park and some shops). Management and mechanical systems are seperate.