Mixed use: Production; Shipping/Receiving; R/D; Office Space
EBOM-2009 IEQp1:Minimum IAQ Performanceposted by Aaron Nelson on
The building has four space types and 20 AHUs. The building lacks any integrated controls, so each AHU operates independent of the other.
Fresh air from different AHUs for the same room
EBOM-2009 IEQp1:Minimum IAQ Performanceposted by Shadi Sobh on
hi all, An existing case were the floor is feed by two (2) variable AHU’s, and a specific room is supplied via two (2) VAVs and each VAV is connected to a different AHU; while calculating the fre
Exhaust Fans in Production area
EBOM-2009 IEQp1:Minimum IAQ Performanceposted by Janna Nash on
For LEED EBOM 2009, IEQp1, are exhaust fan test reports required for every fan or just one per type.
Fresh Air Measurements on Rooftop Units
EBOM-2009 IEQp1:Minimum IAQ Performanceposted by Christopher Pinkowski on
I am applying this credit to ten rooftop units that lack a straight duct section long enough to traverse with a pitot tube.
Adequate measurement equipment and procedures
EBOM-2009 IEQp1:Minimum IAQ Performanceposted by CAIO DE MELO on
We are working on an office building with fan-coils units conditioning office spaces on typical floors and several multi-split ceiling cassette units conditioning technical occupied areas (maintena
Airflow testing service
EBOM-2009 IEQp1:Minimum IAQ Performanceposted by Saul Pichardo, AIA on
Hi All, We are looking for a company in the San Francisco Bay Area who can conduct the airflow tests in our commercial building (in the office area). We are working on a LEED O&M project.
Occupancy rates
EBOM-2009 IEQp1:Minimum IAQ Performanceposted by Nelina Loiselle on
I am not sure why it says on the documentation screen shot that the total occupancy for the VRP calcs should be consistent with occupancy for other credits.
Measurement at DOAS before fixed dampers
EBOM-2009 IEQp1:Minimum IAQ Performanceposted by Noriko Nagazumi on
From the reference guide: "Show compliance with the applicable requirement above through measurements taken at the system level (i.e., the air-handling unit).
ASHRAE 62MZ calculator
EBOM-2009 IEQp1:Minimum IAQ Performanceposted by Mark Frey on
I try to fill out the ASHRAE 62MZ calculator and have some problems with it: 1) We have lots of AHUs in our building (Some Vanitlation systems, some AC-systems and some are only exhaust systems).