5 Year Window and ASHRAE audit v. Cx
EBOM-2009 EAc2.2:Existing Building Commissioning—Implementationposted by Jenny Carney on
All - I always thought that they 5-year exception to the performance period rules on pg. 172 of the reference guide could likely be used for either option, commissioning or the ASHRAE Level II.
Upper limit?
EBOM-2009 EAc2.2:Existing Building Commissioning—Implementationposted by American University on
I'm wondering if all identified ECMs have to be included in a longer term capital improvement plan OR if the audit revealed a project with, say, a 12 year pay back period and high implementation co
Implementing all improvements in one renovations phase at a time
EBOM-2009 EAc2.2:Existing Building Commissioning—Implementationposted by Melissa Merryweather on
We're starting the audits for an EBOM project that is a university building.
Capitol Cost ECMs
EBOM-2009 EAc2.2:Existing Building Commissioning—Implementationposted by Robert Calloway on
When submitting the reports for a LEED RCx project, one of the reports is for Capital Cost Energy Conservation Measures.
Training Program?
EBOM-2009 EAc2.2:Existing Building Commissioning—Implementationposted by Robert Andrews on
Any suggestions on a source for templates that can be used to document a staff training program? I am actually working with LEED EB v2.0, EAc3.1. Thanks!
Recertification
EBOM-2009 EAc2.2:Existing Building Commissioning—Implementationposted by Scott Vitko on
I am unclear as to what the recertification requirements would be for a project that obtained this credit with the original certification about a year ago.
commissioning performance period
EBOM-2009 EAc2.2:Existing Building Commissioning—Implementationposted by Pablo Fortunato Suarez on
This is for a 1st time EBOM project (not recertification). If Six Sigma Projects were initiated 5 years prior to LEED registration but implemented every year thereafter until the present time: 1)
Items to be implemented for EAc2.2
EBOM-2009 EAc2.2:Existing Building Commissioning—Implementationposted by Mark Campbell on
It is clear that the low cost/no cost items uncovered during the investigation phase in EAc2.1 must ALL be implemented to satisfy the requirements of EAc2.2. My Question: Must ALL of the low-cost/