Land clearing debris

NC-2009 MRc2:Construction Waste Management
posted by  Kelly Humphry  on 

I understand that LEED does not count land clearing debris in its construction waste recycling numbers, however, it also does say in the manual that "any construction debris processed into a recycl

2
Default Avatar
Architect, LEED Consultant
Polk Stanley Wilcox Architects
LEEDuser Basic Member
29 thumbs up
Mon Apr 7, 2025, 9:14 am

Has anyone earned this credit without a Waste Management Plan?

NC-2009 MRc2:Construction Waste Management
posted by  Jeff Wiedmeyer  on 

Just wondering if anyone has earned the MRc2 credit without uploading a Waste Management Plan.  And if you did, what sort of Additional Information did your team provide to justify exclusion o

2
Managing Partner
Innovative Workshop Consulting
LEEDuser Expert
22 thumbs up
Thu Sep 30, 2021, 11:08 pm

MRc2 Backup Documentation

NC-2009 MRc2:Construction Waste Management
posted by  Katarzyna Gajewska  on 

Hi there, thanks for looking into my question.

5
Senior Project Manager
Zinner Consultants
LEEDuser Basic Member
110 thumbs up
Mon Nov 23, 2020, 12:32 pm

Waste Diversion

NC-2009 MRc2:Construction Waste Management
posted by  Susan Di Giulio  on 

Hello,

If our project is using Green Halo systems to manage our wastemanagement, do we need to 
submit all the back up documentation for the commingled items?

1
Mon Oct 19, 2020, 5:33 pm

Asphalt Paving Base Material

NC-2009 MRc2:Construction Waste Management
posted by  Randy Weatherly  on 

I understand that I can re-use asphalt and concrete paving on the site for this credit, but does this also apply to the 6" type "A" crushed stone aggregate base below these paving types.

2
Default Avatar
LEEDuser Expert
472 thumbs up
Thu Jul 23, 2020, 4:08 pm

Reclaimed Material as Diverted Waste

NC-2009 MRc2:Construction Waste Management
posted by  Jeannie Rhoden  on 

We used a quarry as an end user where we hauled land clearing debris and dirt/rubble. It has been reclaimed and used as quarry fill. Can this be considered diverted waste?

0

MRc2

NC-2009 MRc2:Construction Waste Management
posted by  Victoria Rios Esteve  on 

Hi! We have a building in the process of certification which changed its initial contractor to another company.

3
Managing Partner
Innovative Workshop Consulting
LEEDuser Expert
22 thumbs up
Mon Oct 21, 2019, 1:57 pm

PCB Waste considered Hazardous Material, not to be tracked?

NC-2009 MRc2:Construction Waste Management
posted by  William LaRose  on 

I am tracking demolition waste from several structures that were removed to make room for my current LEED project.

3
Construction Administrator/ LEED AP
Bywater Woodworks, Inc.
LEEDuser Basic Member
42 thumbs up
Mon Oct 21, 2019, 8:51 am

LEED 2009 NC Material and Resources - Construction Wast emanagement

NC-2009 MRc2:Construction Waste Management
posted by  Judy Bethuy  on 

Do I need track the packaging material from AV and computer equipment as part of the Cpnstruciont Waste Management credit?

1
Mon Oct 21, 2019, 8:57 am

MRc2.2 Requiered information

NC-2009 MRc2:Construction Waste Management
posted by  Victoria Rios Esteve  on 

Hi everyone!

I´m pretty new at LEED certification process, so I will really appreaciate your help. 

1
Mon Oct 14, 2019, 2:15 am