LEED Commissioning vs. "Total Building Commissioning" (TBCx)

NC-2009 EAc3:Enhanced Commissioning
posted by  Matt Nolan  on 

I am seeing more and more project requirements (for new buildings) mentioning TBCx (Total Building Commissioning)- which is based on ASHRAE Guideline 0.

2
Partner
Viridian
LEEDuser Basic Member
154 thumbs up
Thu Jun 30, 2011, 4:01 pm

Late Enhanced Comissioning

NC-2009 EAc3:Enhanced Commissioning
posted by  Carolina Vergnano  on 

Does exist any time limit between the construction conclusion and the start of enhanced comissioning? i.e.

2
Integrated Design & LEED Specialist
SERA Architects
LEEDuser Expert
1361 thumbs up
Tue Apr 26, 2011, 12:42 pm

Enhanced CX 'Design Firm'

NC-2009 EAc3:Enhanced Commissioning
posted by  Julianne Laue  on 

If a firm is a AE firm and are signing the arch drawings, but not involved in MEP...can an engineer in the firm be the CX?

2
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Wed Mar 30, 2011, 8:20 pm