Post a question or comment
Credit Filters
Must be a complete, permanent building or space
Filter by location
Forum
Topic
Replies
Recent

MPR2 LEEDuser Forum questions and comments prior to the 09/05/17 upgrade

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Brian Bartholomew  on 

 Did we lose access to all the MPR2 LEEDuser Forum questions and comments posted prior to the 09/05/17 upgrade?

1
Thu Sep 7, 2017, 6:28 pm

LEED-NC and Interior Fitout

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  CT G  on 

An owner is developing an office building which is to 75% occupied by one company (different from the owner developing the building).

13
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Apr 8, 2021, 1:36 pm

dividing project during execution after design final review

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Piotr Nowinski  on 

Hello We are working on the project, which include 3 independent buildings: A, B & C (each 17 stories above grade has own mechanic, energy system and entrances ) and 3 floors underground parkin

1
Fri Feb 1, 2013, 10:45 pm

Clarification for LEED CI

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Rebekah Burke  on 

If we are doing a tentant improvement for the entire interior of a building, is it eligible to be certified under LEED-CI.

1
Mon Dec 2, 2013, 3:59 pm

Commercial Office - Rating System selection

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Rohit Jagnani  on 

I have a client looking for LEED certification of its Commercial offices.

1
Tue Jan 7, 2014, 3:46 pm

Permanent Land /Space Requirement (MPRPp2)

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  al-emran hossain  on 

Hi LEED Expert , We want to know about Minimum Program Requirement (MPRPp2)of permanent space/land matter. Our client has 20 years lease land from BD Gov and build NC factory as a LEED Project .

1
Sun Mar 27, 2016, 10:49 pm

Calculating parking area

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Sean Hogan  on 

I have a project seeking certification which has approximately 750 surface car parking spaces.

1
Fri Jul 12, 2013, 6:06 pm

Technical service building - Healthcare v2009

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Jonathan Landry  on 

Hello fellow LEED experts, my client is confused on wether or not their services buildings has to be include in the current certification or could be certificated separately.

1
Mon Jan 23, 2017, 7:14 pm

Two-story office building attached to warehouse

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Silvia Ruiz  on 

Hi, I am working on a project that consists of a two-story office building attached to a warehouse, both of which belong to the same owner.

1
Tue Nov 5, 2013, 4:07 pm

Permanent building - envelope construction

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Jeannie Rueter  on 

We have a client that wants to reduce costs for a warehouse by using a tensioned fabric structure rather than a metal building. My first thought is that it might be considered impermanent.

1
Tue Oct 7, 2014, 1:47 am