Strip out plan

CI-2009 MRc2:Construction Waste Management
posted by  Graham Langton  on 

We are tendering out project in 2 phases. 1 contractor will be brought on to provide a strip out (typical demolition services of a CI project).

2
Default Avatar
LEEDuser Expert
472 thumbs up
Wed Dec 17, 2014, 11:13 am

Can we earn this though new building

CI-2009 MRc2:Construction Waste Management
posted by  Mathilda Jonsson  on 

Hi all! I'm working on a project which seeks LEED CS for the base building and LEED CI for a companys spaces.

6
Director, Project Manager
Delos Living
LEEDuser Basic Member
0 thumbs up
Tue Feb 5, 2013, 9:43 pm

Non-recyclable Debris

CI-2009 MRc2:Construction Waste Management
posted by  Alejandra Feliciano  on 

Hello, We have a CI project undergoing demolition where we needed to excavate under an existing concrete slab. After the slab was removed, we found 'garbage' under the slab.

3
Tue Sep 18, 2012, 7:02 pm

Commingled materials?

CI-2009 MRc2:Construction Waste Management
posted by   Habitech Distretto Tecnologico Trentino  on 

Hello. We are working on a CI project. We have only three types of waste (mixed materials, mix of concrete and mix of gyps), with three different containers.

3
Tue Mar 29, 2011, 4:14 am