Recycled content in Steel frame of facade
NC-2009 MRc4:Recycled Contentposted by Indochine Engineering VN on
Hi, I would like to ask in case that facade manufacturer cannot confirm recycled content in their steel frame of facade, can I use default number 25% recycled content for steel product as stated in
PARTITIONS ARE CONSIDERED FURNITURE?
NC-2009 MRc4:Recycled Contentposted by Florinda Garcia on
I would like to know if i have to consider the partitions in the LEED budget.
exchange rate
NC-2009 MRc4:Recycled Contentposted by jorge calderon on
Hi, I have 3 questions 1-I bought my materials in Mexican pesos, to fill the excel table and make all the calculations, are those in dollars? 2. If yes,which exchange rate should I use? 3.
Recycled content in Broadloom Carpet
NC-2009 MRc4:Recycled Contentposted by michael giannini on
I was redirected to this forum from Tristan Roberts i am trying to get some important info on recycled content in broadloom .
Supplementary Cementitious Materials
NC-2009 MRc4:Recycled Contentposted by Shawn Keith on
I have my cement tracker all filled out.
Question about cut sheets
NC-2009 MRc4:Recycled Contentposted by Magda Aghababyan on
My project uses lot of steel and that is a very large portion of the total material budget. The supplier has not provided cut sheets to confirm the recycled content of steel.
LEED Form MR 4
NC-2009 MRc4:Recycled Contentposted by juan pena on
The assembly as % of product section found in the MR 4 form is already prefilled with 100% for all materials. Is this correct?
Reused material
NC-2009 MRc4:Recycled Contentposted by Erin Holdenried on
If a project is not pursuing MRc3, can reused material count towards MRc4 instead?