Hi All.
Is this credit specifically for office waste or all waste streams?
I’m working on a large industrial factory building, and whilst the operator has a policy of recycling materials from the manufacturing process this is a very different process to the occupant-led recycling facilities and plan.
Would in internal layout drawing need to show the recycling areas on the factory floor?
Many thanks.
Kit
Lisa Fabula
Sustainable Project ManagerKEMA Services
42 thumbs up
September 9, 2011 - 1:42 pm
The prerequisite requires a description and drawing that shows the "dedicated recycling storage areas" that are used to collect "paper; corrugated cardboard; glass; plastics; metals"; this may be quite different than the manufacturing process that reclaims pre-consumer material for reuse/recycling.