We are in the PP but do not have our low-water landscaping installed. A contract will be signed to install it prior to the end of the PP. Has anyone obtained the credit this way? The client's landscape architect said we could. I think that only works for LEED BD+C. Anyone out there have experience with this? Thank you.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Ben Stanley
Senior Sustainability ManagerWSP - Built Ecology
LEEDuser Expert
250 thumbs up
September 24, 2015 - 1:23 pm
Is the design complete? If so and if the contract gets signed to do the work during the performance period, I could see GBCI considering this approach but I haven't seen this type of strategy approved in the past. If the installation timeline is relatively short like less than 3 or 4 months, another strategy would be to submit this credit during the final review phase. I think that approach would have a better chance of success.