The GBCI has decided that net-zero projects must buy additional EAc6 green power if the actual energy use for two-years post-occupancy does not match the GBCI approved results from EAc1/EAc2. (Refer to LI 10219 regarding the net-zero case.)

Projects would be better off claiming 99.9% energy cost reduction than trying to claim net-zero.