We are currently adjusting a few credit submissions based on Prelim. Construction review feedback and one credit will change material costs from $35k to $100k. If this value was also included in another credit that has already been awarded does that credit also need to be modified and re-submitted?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
TODD REED
Energy Program SpecialistPA DMVA
LEEDuser Expert
889 thumbs up
December 30, 2015 - 3:26 pm
You can look at this two ways. If the value does not change achievement or point total in the other credit, then you could just provide a narrative to the reviewer in regards to this. The reviewer will check whether you do anything or not.
The other way and what I consider to be the proper way is to make the necessary changes in all related credits. This is what you are supposed to do. It shows the reviewers that you are being professional and not trying to cover anything up.
Either way would work, but since you are in the prelim, its not that hard to just make the changes and resubmit. It does not cost anymore.