I am not quite sure if the approach discussed in my project team is a viable way to achieve this credit and would like to check back with you. The project is in a dense city location and will be impermeable to 80-90%. There is zero lot line on 2 sides, a zero lot line neighbour on the third side and a basement for most of the site, with the building and open space above. There will be a strip next to the building insite the site limits, 5 metres wide, that is part of an adjacent plaza, has no basement below and will have an almost impermeable surface.
This strip next to the building is the only place where rainwater could be infiltrated. The project team proposed to build a structure below this strip that will infiltrate rainwater and retain any rainwater up to the required percentile that exceeds that infiltration rate. The structure will be covered and not be seen from the surface. It would be designed to retain and infiltrate percentile rain as required for the pursued number of points.
Some questions arise:
- Given that there is a 5 metre wide strip next to the building footprint I assume this project cannot be taken as zero lot line? Is there a definition of “…nearly aligns with the site limits”?
- Is this kind of covered, underground infiltration trench compliant with the requirements “best replicating natural site hydrology”, is this a LID measure?
Thanks for any views, tips and hints.
Michael DeVuono
Regional Stormwater LeaderArcadis North America
LEEDuser Expert
187 thumbs up
September 15, 2017 - 6:31 am
What you're describing is definitely a GI/LID strategy, however, I would be a little leery about putting an infiltration system that close to a building with a basement.
I'd rather see some form of slow release detention where the trench is lined, and vegetation and trees are used to evapotranspirate the runoff.
Since this is a relatively untested credit right now, I'm not sure if they're accepting slow release as a strategy yet.
Jens Apel
134 thumbs up
September 15, 2017 - 6:50 am
thanks for that quick response. Indeed the proximity to the basement is an issue, but the basement is below ground water level and will be constructed water tight anyway. There are surely a lot of questions to be answered during design (including hydrological feasibilty), I was more concerned about general GI/LID.