We have just received our review for combined D&C. What is the deadline to respond to the reviewer's comments?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium forForum discussion
LEED Reviews: Appeals, Design/Construction Submittals, and more
We have just received our review for combined D&C. What is the deadline to respond to the reviewer's comments?
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
Charles Nepps
NH Green Consulting97 thumbs up
July 29, 2014 - 3:22 am
25 workings days
Ian McCall
Environmental Engineer13 thumbs up
June 16, 2015 - 3:47 am
Hello,
What happens after the 25 working days have expired? We have a project that will probably take a year to re-submit. What should we expect being overdue by 1 year?
Regards,
Ian
Charles Nepps
NH Green Consulting97 thumbs up
June 16, 2015 - 4:03 am
Ian, the standard USGBC reply is:
"The 25 business day duration stated in our emails when we return a review to the project team is a suggestion that is intended to encourage project teams to maintain progress. We appreciate your letting us know if you will need more time. Please take the time you need to prepare a thorough response to review comments, or to prepare your appeal. Please note, all O+M projects are subject to all performance period criteria, and this information is only relative to clarifications between rounds of review."
You should contact them and let them know you are anticipating needing a year to respond to the review comments, and they will add the comment to the project record.