Hello!

So I recieved the following review comment for the Option 1, Surrounding Density credit:

1. It does not appear that all buildable land within one-quarter mile of the project boundary has been shown in the vicinity map
and included in the calculations. The documentation indicates that only the site area for the buildings included in the
calculation as buildable land. However, all buildable land within one-quarter mile of the project boundary must be included.

BUT, my question is, why do I need to include ALL buildable land, why not stop after the credit requirement was met?  It seems unnecessary work to continue adding all buildable land within the one-quarter mile of the project boundary when i dont it to meet the credit requirements. Does anyone have any insight as to why this extra work would be necessary?

Thank you!