When submitting our preliminary design review for a LEED for schools project, we did not submit any Construction Phase Credits. Was this an error? We have yet to complete most of the construction related credit forms but I do not know if these should be submitted with our final design review or if we should wait until submitting our construction preliminary review.
You are are not allowed to submit construction credits at the design reviews. You need to submit them at construction review. However, you can submit additional design credits at the construction review.