Hi,

We are working on a project where our next step is the Design Final Review (Responding to the GBCI reviewer comments from the Design Preliminary Review). It so happens that we have a lot of the construction credits (not them all) ready to submit. Is it possible to submit construction credits during either of the Design Review (Preliminary or Final) stages?

From what I have read on LEED User so far, it seems as if we will need to wait until the Construction Preliminary Review stage to upload any of the construction credits. The same post says that it is possible to upload design credits during construction reviews but not construction credits during design reviews.

All feedback is welcome and thank you in advance for your assistance.