Dear Sirs,
i am working on a CI project and we have been awarded 48 points in the design stage credits , how ever we are targeting gold, and we still have 13 points to be earned in construction stage , total of 61 , but the project team is a little bit worried we wouldn't achieve gold, and we were negotiating working on green education program, but since it is considered a design credit we wanted to know is it possible to submit this credit as an appeal but after the construction phase preliminary review (in case we didn't get the total 13 construction points)?
Michael Smithing
Director - Green Building AdvisoryColliers International Ltd.
304 thumbs up
November 12, 2013 - 4:17 am
There is no requirement to submit design credits with the design review - you can also submit them with the construction review. Depending on where you are in the process, you can submit the Education Program with the Construction Preliminary or Construction Final review. If possible, submit with the Preliminary review so that you get a chance to address any comments that the review team may have. You will not have to appeal (and pay the additional fee) as this will be part of the Construction Review.