The performance period for our project is only 90 days. Does the contract for SSc5 offisite land restoration need to be longer than the performance period (such as a 1 yr contract) or can we contract for just the 90 day performance period?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Varun Chandra
May 4, 2020 - 5:09 pm
Hello, Could you share who you used for the contract for SSc5 offisite land restoration? Thanks!
Trista Brown
Project DirectorWSP USA
456 thumbs up
May 26, 2020 - 3:54 pm
Hi Randi - I pulled the below from LEEDuser's FAQ for this credit:
Is there a requirement for how long financial support or labor services must be provided to an off-site area?
There is no requirement that speaks to this directly. The commitment should be long enough to deliver meaningful benefit to the off-site property and must cover the minimally applicable performance period for the LEED project. Many project teams choose to do either a one- or two-year contract. Consult with the property owner and consider your restoration goals when determining the appropriate length of time for your contract.