Hi. One of the projects in which I'm involved will have on-site HVAC duct manufacture. Does this practice has any inconvenient for the compliance with the credit IEQc3.1? We should manage that once installed all the ductwork will be sealed as usual, but I haven't read a lot about requirements for on-site duct ellaboration. If anyone could comment on this, it will be much appreciated!
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Allison Beer McKenzie
Architect, Director of SustainabilitySHP Leading Design
LEEDuser Expert
646 thumbs up
December 5, 2011 - 2:21 pm
You should be fine as long as it is protected when it stored as well as once it is installed.
Mauricio Ramirez
34 thumbs up
December 6, 2011 - 7:04 pm
Thanks Allison. I was looking for all the RefGuide and other documents and couldn't find any info about on-site building. But I think as you say, that storing and protecting on installation will work. Tx.
G R
February 5, 2014 - 12:56 pm
Hi Allison,
I have a similar question here. Is the ductwork stored and on the floor also need to be sealed with the blue wrap at both ends or covering them with plastic will suffice? Please let me know....Thanks.