there are 8 stops/stations within 1 mile radius form our project serving 47 public bus/light rail lines, and 2 of them are municipal public transportation hubs that connect the vicinity to downtown areas. All these buses/light rail can provide at least 2,500 transit rides a day.
Shuttles bring the 8 stops/stations closer to the project. Staff and transients can get to them within 10 minutes via 2 shuttle lines. Besides, the capacity, schedule and frequency of shuttle service are adequate for all project occupants.
The above generally describes how our project is going to seek SSc4.1. Can anybody advise if it works? And, can the 8 stops with more than 2,500 rides per day contribute to exemplary performance Option 2 -DoubleTransit Ridership as they are beyond 1/4 miles distance?
Many thanks!
Noriko Nagazumi
Woonerf Inc.74 thumbs up
February 8, 2015 - 10:05 pm
Hi Weidong,
Please be sure to calculate only rail stations within 1/2 mile and bus stations within 1/4 mile of the project main entrance. GBCI may not accept transportation outside the distances stipulated. You may try to convince them if there are special reasons though.