there are 8 stops/stations within 1 mile radius form our project serving 47 public bus/light rail lines, and 2 of them are municipal public transportation hubs that connect the vicinity to downtown areas. All these buses/light rail can provide at least 2,500 transit rides a day.

Shuttles bring the 8 stops/stations closer to the project. Staff and transients can get to them within 10 minutes via 2 shuttle lines. Besides, the capacity, schedule and frequency of shuttle service are adequate for all project occupants.

The above generally describes how our project is going to seek SSc4.1. Can anybody advise if it works? And, can the 8 stops with more than 2,500 rides per day contribute to exemplary performance Option 2 -DoubleTransit Ridership as they are beyond 1/4 miles distance?

Many thanks!