Hello, I am working on a C&S project. The minimum parking capacity set by local zoning is 165 parking spots. The project has 165 spots exactly. The project size is 86000 sq ft. Van pool would be about 5 spaces. The question is can the Van pool spaces be marked, however, assigned until there is a demand. Once there is a demand or want for the spot. The person who has the spot would be reassigned to another location and the person operating the car pool / van pool would then take over the spot. There is no issue with the # or location of spots, but the owner does not want the spots to sit empty unless there is a demand. Is this okay to claim credit? Thanks!
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Marilyn Specht
Vice President & Managing Principal, US SustainabilityIntroba
LEEDuser Expert
51 thumbs up
July 7, 2016 - 7:08 pm
Hi Troy, my gut says this might be a long shot but if you feel confident your project still meets the credits intent, I would provide a narrative explaining the case. I might also include a letter from the owner demonstrating some kind of evidence that they are committed to enforcing this to help support your claims.